Construction of 33/13.8KV S/S 7724 for Water Treatment Station
Electrical Works – Construction of 33KV Substations in AlKarj area No.7724 and connection of cable circuits from substation 7724 to substation 7711 (2008 – 2010)
Project Date2018-12-20
ClassificationPOWER
Project Cost15,499,528
Project Duration24 Months